Forensic Planning for a thorough claim analysis

The Pasay Harbor reclamation involved the construction of two artificial islands in Manila Bay, an ambitious project led by Jan De Nul and Boskalis, under a FIDIC Yellow Book contract. The aim was to develop valuable land space for future economic growth, but as is often the case with large-scale projects, Pasay Harbor faced delays that led to claims. These challenges required a thorough analysis, and I was brought in as a Forensic Scheduler.

Wesley van der Burg (founder @ BAEKEN) contributed to this project while working for Primaned project consultancy, part of Eiffel Projects, prior to founding BAEKEN.

Why was Wesley needed?

The execution of Pasay Harbor was hindered by several bottlenecks: the quality of the original baseline program was insufficient, there were inconsistencies between the progress updates, and the logic in the schedules did not align with the contractual documentation. This made it difficult to conduct a thorough analysis of the project progress, creating a need to address these shortcomings. Therefore, I was asked to bring order to the situation and establish a new, consistent foundation for further project analyses.

How did I approach the project?

  1. Creating a robust baseline

    Upon arriving at the project, I began by analyzing the existing baseline schedule and progress updates, which revealed that the quality could be improved. I used these findings to develop a new, robust planning that would serve as the basis for further progress measurements and subsequent delay analyses. With this improved baseline, we could work with greater confidence, significantly enhancing the process for critical path analysis and performance. This provided a solid foundation for managing the time and scheduling aspects of the project.

  2. Thorough Forensic Analysis

    I conducted a forensic analysis of the delays incurred, which involved a comprehensive assessment of all scheduling documents, identifying the primary causes of delay, and mapping the consequences of these delays. A detailed report was prepared, describing each delay and its impact on the project milestones. This report distinguished between the responsible parties and outlined who was accountable for which overruns. It served as the basis for a formal Extension of Time claim.

  3. Improving Communication and Transparency

    In addition to the technical aspects, it was also crucial to enhance communication and transparency within the project team. By utilizing the reconstructed schedule, I ensured that everyone, from project managers to execution teams, was informed of the current status and any bottlenecks that needed to be addressed. This facilitated a streamlined approach where all parties involved shared the same expectations and could better anticipate changes.

Wat has been used?

Primavera P6

for establishing a new baseline and critical path analysis

Time-window analysis

for applying forensic planning

 

Benieuwd wat ik voor jouw project kan doen?
Wesley van der Burg

 

 

Curious if we can do something for you? Or check out similar projects.

This field is for validation purposes and should be left unchanged.

Of bekijk andere projecten

De Knoop @ Rijksvastgoedbedrijf

When Rijksvastgoedbedrijf (RVB) acquired the former Knoop barracks in Utrecht in 2011, it had the ambition to transform

  • Area development

Business Park @ Aviolanda

Business Park Aviolanda houses companies and training institutes in the field of aircraft engineering and maintenance.

  • Area development

Sustainable energy use @ Croonwolter&Dros

Commissioned by Vattenfall, Croonwolter&Dros is realizing the heat station “De Sleutel” (The Key) near Leiden, alongside

  • Energy transition
  • Technologie en innovatie
  • Technology and Innovation

Lighting and Traffic Management Systems @ Vialis

Since October 1st, 2021, Vialis, commissioned by Rijkswaterstaat, has been replacing various technical systems under the

  • Technologie en innovatie
  • Technology and Innovation

Road maintenance in the eastern Netherlands @ Haskoning

To keep the national roads of the East Netherlands district (ON) in optimal condition, Rijkswaterstaat (RWS), through it

  • Technologie en innovatie
  • Technology and Innovation
This site is registered on wpml.org as a development site. Switch to a production site key to remove this banner.